Permit Guide for LA Fire Rebuilds
What you need to submit, and how long it takes — broken down by jurisdiction.
LA County Dept of Regional Planning
Altadena / Unincorporated LA County
- →Like-for-like rebuild (same footprint, up to 200 sq ft or 10% larger): eligible for fast-track — approved in 1–3 business days
- →Pre-approved standard plans available — significantly reduce design cost and review time
- →Self-certification pilot for simple projects: architect certifies code compliance, county reviews administratively
- →Bundled Projects Pilot: submit home + ADU in a single application
- →2,600+ permits issued as of early 2026; ~3,340 still under review
- →Fee waivers available — confirm current status with county
Los Angeles Dept of Building & Safety (LADBS)
Pacific Palisades / City of LA
- →Single-family permits now processing 3× faster than pre-fire baseline
- →Average permit wait: ~49 days across all permit types (varies by complexity)
- →Permit fees currently waived under Emergency Order No. 7
- →Coastal Zone: many Palisades properties require CA Coastal Commission approval — adds weeks to months and restricts height/massing. Check your parcel before designing.
- →Commercial Village properties: additional Neighborhood Specific Plan review required
Documents Required for Permit Submission
Incomplete applications are the #1 cause of delays. Have everything ready before you submit.
- ✓Site plan showing lot boundaries, setbacks, and structure footprint
- ✓Floor plans (all levels) with room labels and dimensions
- ✓Elevations (all four sides) showing heights and materials
- ✓Foundation plan (or geotechnical report if on hillside or fill)
- ✓Energy compliance documentation (Title 24)
- ✓Fire-hardening compliance checklist (Chapter 7A)
- ✓Clearance letter from CalRecycle / LA County confirming debris removal complete
- ✓Proof of property ownership (deed or title)
- ✓Contractor license number (CSLB) for permit application